Previous
Next

Tenant
Ecom Express

Area
500,000 Sq. Ft.

Timeline
Q1 2016 - Q3 2016 (Phase I) | Q2 2019 - Q3 2020 (Phase II)

Location
Vill. Patherheri, Haryana

What we did
Land Acquisition, All Compliances, Design & Build Contract, Leasing, Complete BTS (Build to Suit) Solution
This Project was started in January 2016 and was completed in July 2016. Being a Turnkey project, Pragati handled the Compliances and Leasing with Ecom Express.
Delivering the phase I (500,000 Sq. Ft.) of this project in a 6-month timeline was a closely knitted disaster waiting to happen but thanks to the streamlined group execution, the project was delivered without any problems.
The client and investors have expressed their satisfaction and have engaged with Pragati for yet another project, expanding into phase II in 2020.