Pragati Engagement
- Identify suitable land for the development
- Onboard Investor for Land Investment and Development
- Conversion of the land for Warehouse Use
- Seeking all approvals (Building plan, Fire, Forest, Environmental etc)
- Get post construction approvals
- Handover and Commence Operations


Pragati Value Add
- Completed the Land acquisition in 2 months
- Identified Investor and onboarded for purchase and development of the project
- Got the Change of Land use in 45 days
- Got all approvals with-in 70 days (NHAI, Forest, Building Plan, Environmental, Fire Scheme, CTE etc)
- Constructed the park in 8 months time
Delhi NCR (Amazon - DEL 5)
-
Total Area
21 Acres
-
Built Up
0.65 Million sq.ft. (including 50% mezzanine)